[ARCHIVED] 8000 North Update

8000 North Rendering

Check out this article about 8000 North in the Summer 2019 issue of the DDC Journal.

Update, July 15, 2019 - Construction of 8000 North Concrete Panels Complete

A significant milestone has been reached as the exterior "skin" of the concrete panels for the residential tower for 8000 North have been completed. To showcase the panels, a sample was staged on the construction site on July 15th. Everyone is encouraged to visit the site along the Oakton Street frontage to see the panels as well as the significant foundation work completed in Phase 1 of the project. Each panel is numbered and will be delivered from the manufacturing facility in Wisconsin to the site in the proper sequence as the superstructure is developed.

The 8000 North project being constructed on the northwest corner of Lincoln Avenue and Oakton Street in Downtown Skokie is a mixed-use development that will feature a 153-unit, 12-story luxury apartment building and ground-floor retail space. The development also includes a six-story parking garage with 73 public parking spaces for the development and Downtown Skokie visitors beyond the 192 private resident parking spaces. The residential building will offer studios, one and two bedroom units, along with a number of three-bedroom residences on the twelfth floor. The building’s rooftop amenity level includes a fitness center, great room with fireplace, outdoor barbecue area, coffee lounge, garden areas and other amenities – including views of the Chicago skyline - for building tenants to enjoy. 

Phase I of the 8000 North Development, which began in fall 2018, was recently completed. This construction phase included installation of nearly 100 caissons at approximately 60 to 70 feet in depth to support the garage and residential building foundations, grade beams for all foundation work, stormwater storage tanks and the sanitary sewer connections.  In addition, all underground utilities have been installed and the foundations for both the residential building and parking garage an in place. With all of the Phase I work now complete, the project awaits additional governmental approvals before moving to Phase II which will include vertical construction of both the garage structure and residential building. Building occupancies are expected to begin in mid- to late-2020.

The 8000 North development team includes renowned architects from Lucien Lagrange Studio, Pamela Self Landscape Architects, General Contractor W.E. O’Neil and several other preeminent development professionals. More information and updates on the 8000 North development.


Facebook Twitter Email

Other News in 1. Latest News

Holiday string lighting

Recycle Your Holiday Lighting

Posted on: November 28, 2023
Flu shot being administered at Skokie Flu Shot Clinic

Respiratory Viruses Are On the Rise

Posted on: November 28, 2023
Gift cards on display

Support Skokie Families in Need

Posted on: November 20, 2023
Cookie Walk 2023 promo image (text overlaid on chocolate chip cookie)

Inaugural Holiday Cookie Walk, December 2

Posted on: November 15, 2023
Ambulance 17

Updating Skokie's Emergency Vehicle Fleet

Posted on: November 14, 2023
Snow shoveling

Sign Up for the TeenLink Program

Posted on: November 14, 2023
Skokie Village Hall

Apply to Be Skokie Village Clerk

Posted on: November 7, 2023
STAT Commission logo

Submit Tech Excellence Award Nominations

Posted on: October 31, 2023
counseling session

Village Offers Support Resources

Posted on: October 27, 2023
fall leaf collection operations

Leaf Collection and Yard Waste Pickup

Posted on: October 2, 2023
Solar-powered street light

Village Pilots Solar-Powered Street Light

Posted on: September 27, 2023
Skokie Village Hall

Village Recognized for Innovative Services

Posted on: September 25, 2023
COVID vaccine administration

Updated COVID-19 Vaccine Recommended

Posted on: September 19, 2023
STAT Commission logo

Provide Your Input On Technology Issues

Posted on: September 18, 2023
Traffic Cones

It's Road Construction Season

Posted on: April 11, 2023
Heating Cooling Center Graphic (PNG)

Warming and Cooling Centers in Skokie

Posted on: November 16, 2022